PETITION NO. 1323 – Windham Solar LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, maintenance and operation of three 2.0 Megawatt AC and two 1.0 Megawatt AC solar photovoltaic electric generating facilities on an approximate 43 acre parcel located at 134 Bilton Road, Somers, Connecticut.
PROCEDURAL CORRESPONDENCE
Incomplete Letter from the Council to Windham Solar, LLC, 9/6/2017
Extension Request and CSC Approval, 10/4/2017
State Agency Comment Memo, 10/30/2017
Council Letter to the Town of Somers, 10/30/2017
Council Letter to the Town of Enfield, 10/30/2017
Field Inspection Review, 10/30/2017
Response to Set One Interrogatories, 11/27/2017
Interrogatories Set Two, 11/30/3017
Comment Letter from the Drinking water Section of the Department of Public Health, 11/30/2017
Response to Interrogatories Set Two, 12/20/2017
DECISION
Council Decision and Staff Report, 1/22/2018
DEVELOPMENT AND MANAGEMENT PLAN (D&M Plan)
Development and Management Plan,10/15/18
DEEP Notice of Permit Authorization to S. Broyer, 10/31/18
Council Decision Letter and Staff Report on D&M Plan, 11/09/18
Phase II Environmental Assessment, received 12/11/19
Phase III Environmental Assessment, received 12/11/19
Council Acknowledgement of Environmental Assessments II and III, 12/16/19
Development and Management Plan Modification Request, 10/27/20
Council Decision on D&M Plan Modification Request, 11/04/20
Development and Management Plan Modification and Extension Request, 11/11/20
Council Response to D&M Plan Modification and Extension Request, 11/20/20
Construction Status and Request for Extension, 01/13/23
Council Extension Decision, 01/18/23
Request to Use a Sheep Grazing Plan, 03/31/23
Council D&M Plan Revision Decision, 04/11/23
Request for Additional Extension of Construction Time and Council Extension Decision, 09/26/24