DOCKET NO. 494 - Cellco Partnership d/b/a Verizon Wireless application for a The Towers LLC Certificate of Environmental Compatibility and Public Need for the construction, maintenance, and operation of a telecommunications facility located south of Chestnut Hill Road at the intersection with Grilley Road and Lyman Road (Parcel No. 101-1-5B), Wolcott, Connecticut.
APPLICATION (recd. 09/02/20)
Narrative
Attachment 1 - Wolcott South Facility - Factual Summary and Project Plans
Attachment 2 - Certificate of Service of Application on Government Officials; and List of Officials Served
Attachment 3 - Legal Notice in the Waterbury Republican-American
Attachment 4 - Notice to Landowners; List of Abutting Landowners; Certificate of Service
Attachment 5 - Federal Communications Commission Licenses
Attachment 6 - Coverage Maps - Location of Wolcott South and Surrounding Cell Sites
Attachment 7 - Antenna and Equipment Specifications
Attachment 8 - Site Search Summary
Attachment 9 - Visibility Analysis
Attachment 10 - USFWS and NDDB Compliance Determination
Attachment 11 - Wetlands and Vernal Pool Impact Analysis
Attachment 12 - Preliminary Historic Resources Determination
Attachment 13 - Farmland Soils Map
Attachment 14 - General Power Density Table
Attachment 15 - FEMA - Flood Insurance Rate Map
Attachment 16 - Federal Airways & Airspace Report
Attachment 17 - Land Lease Agreement - Redacted
Bulk:
Town of Wolcott Zoning Regulations
Town of Wolcott Plan of Conservation and Development
Town of Wolcott Inland Wetlands and Watercourses Regulations
Technical Report
PROCEDURAL CORRESPONDENCE
Council Letter to the Town of Wolcott, 09/03/20
Council Letter to the City of Waterbury, 09/03/20
Council Request for a Completeness Review Extension, 09/10/20
Council Completeness Review, 10/08/20
Council Decision on Motion for Protective Order, 10/09/20
Council Interrogatories to Verizon, Set One, 10/21/20
Council Letter Acknowledging AT&T's Request for Intervenor Status, 10/30/20
Council Decision on AT&T's Request for Intervenor Status, 11/20/20
Council Interrogatories to Verizon, Set Two, 11/23/20
Council Interrogatories to AT&T, Set One, 11/23/20
Council Extension Request to Render a Final Decision, 02/25/21
STATE AGENCY COMMENTS
State of Connecticut Council on Environmental Quality Comments, 09/30/20
Department of Transportation Comments, 11/02/20
MUNICIPAL COMMENTS
PUBLIC OFFICIAL COMMENT
TELECOMMUNICATION CARRIER CORRESPONDENCE
HEARING INFORMATION
Pre-Hearing Tele-Conference Memorandum, 11/12/20
Remote Hearing Procedure Memorandum, 11/19/20
December 8, 2020 Hearing Documents, 10/09/20
1. Instruction for Public Access to Remote Public Hearing
2. Public Hearing Notice
3. Hearing Program
4. Citizens Guide to Siting Council Procedures; and
5. Proposed Facility Site Plans
Schedules
Schedule, 09/03/20
Schedule, 10/08/20
Schedule, 11/20/20
Schedule, 04/19/21
Service Lists
Service List, 09/03/20
Service List, 11/19/20
Service List, 04/11/24
Hearing Programs
Hearing Program
Transcripts
Hearing Transcript 2 p.m., 12/08/20
Public Session Transcript 6:30 p.m., 12/08/20
Council Transcript Memorandum, 12/14/20
PARTIES AND INTERVENORS
Applicant - Cellco Partnership d/b/a Verizon Wireless
Signed Protective Order, 10/08/20
Applicant Responses to Council Interrogatories, Set One, 11/13/20
Applicant Sign Posting Affidavit, 11/18/20
Applicant Responses to Council Interrogatories, Set Two, 12/01/20
Correspondence
Applicant Response to Council Request for a Completeness Review Extension, 09/10/20
Applicant Pre-Hearing Submission, 12/01/20
Applicant Response to Council's Request for Extension to Render Final Decision, 02/26/21
Motions and Objections
Cellco Motion for Protective Order, 09/09/20
Post Hearing Brief and Draft Findings of Fact
Intervenor - New Cingular Wireless PCS, LLC (AT&T)
Exhibits
AT&T Request to Intervene, 10/30/20
AT&T Responses to Interrogatories, Set One, 12/01/20
Correspondence
AT&T Pre-Hearing Submission, 12/01/20
Motions and Objections
Post Hearing Brief and Draft Findings of Fact
COUNCIL'S DRAFT FINDINGS OF FACT
Council's Draft Findings of Fact, 05/06/21
FINAL DECISION
Council's Final Decision Documents, 05/24/21
DEVELOPMENT AND MANAGEMENT PLAN (D&M PLAN)
D&M Plan, 03/24/22
D&M Plan Schedule, 03/24/22
Council D&M Plan Interrogatories, 04/18/22
Request for Extension to Respond to Council D&M Plan Interrogatories and Council Approval, 04/29/22
D&M Plan Schedule, 05/02/22
Council Request for Additional Time to Render the D&M Plan Decision, 05/02/22
Verizon Responses to D&M Plan Interrogatories, 05/04/22
Verizon Response to Council Request for Additional Time to Render the D&M Plan Decision, 05/04/22
D&M Plan Schedule, 05/04/22
Council D&M Plan Decision and Staff Report, 05/27/22
Request for Extension and Council Extension Approval, 09/16/22
Notice of Commencement of Construction, 02/28/23
Request to Change Approved Remote Radio Head Equipment Model and Council Decision, 05/26/23
Request for and Additional Extension and Council Extension Approval, 06/13/23
Request for Proposed Equipment Modifications, 10/18/23
Council D&M Plan Revision Decision, 10/20/23
Request for Transfer of Certificate, 03/22/24
Request for Transfer Contact Information, 03/22/24
Council Decision on Transfer of Certification Request, 04/11/24
Council May 27, 2022 D&M Plan Decision Condition No. 1 Submission - AT&T's Final Emergency Backup Generator and Fuel Tank Configuration, 07/22/24
AT&T Structural Analysis
AT&T Mount Analysis
Council Decision on D&M Plan Condition No. 1, 08/15/24
Request for an Additional Extension and Council Extension Decision, 09/25/24