APPLICATION (received 04/21/17)
Tab 1 - Factual Summary and Project Plans
Tab 2 - Certificate of Service of Application on Government Officials and List of Officials Served
Tab 3 - Legal Notice in the Connecticut Post
Tab 4 - Notice to Landowners; List of Abutting Landowners; Certification of Service
Tab 5 - Federal Communications Commission Licenses
Tab 6 - Coverage Maps - Easton and Surrounding Cell Sites
Tab 7 - Antenna, Equipment and Generator Specifications
Tab 8 - Site Search Summary
Tab 9 - Visibility Analysis
Tab 10 - USFWS Compliance Determination
Tab 11 - Connecticut DEEP/NDDB Determination
Tab 12 - Wetlands Inspection Report
Tab 13 -State Historic Preservation Office Determination
Tab 14 - FCC RF Compliance Assessment and Report
Tab 15 - FEMA - Flood Insurance Rate Map
Tab 16 - Waiver of Further Municipal Consultation - Towns of Easton and Fairfield
Tab 17 - FAA Aeronautical Evaluation
Tab 18 - Option and Ground Lease Agreement between Homeland Towers, LLC and the Town of Easton
Bulk Items
Town of Easton Zoning Regulations, 11/14/98
Town of Easton Plan of Conservation and Development 2006, effective 07/01/07
PROCEDURAL CORRESPONDENCE
Council Letter to the Town of Easton, 4/26/2017
Council Letter to the Town of Fairfield, 4/26/2017
Council Interrogatories to Applicant, 5/17/2017
Pamela Westmoreland Request for Party Status, 5/18/2017
Field Review Notice, 6/13/2017
Council Memorandum Regarding Town of Easton Planning and Zoning Commission letter, 07/18/17
STATE AGENCY COMMENTS
Comments from the Department of Transportation, 5/16/2017
Comments from the Drinking Water Section of the Department of Public Health, 5/30/2017
MUNICIPAL COMMENTS
PUBLIC OFFICIAL COMMENTS
TELECOMMUNICATION CARRIER COMMENTS
HEARING INFORMATION
Hearing Notice Package, 5/12/2017
Pre-Hearing Teleconference Memo, 5/17/2017
Council's Administrative Notice
Hearing Procedures Memo, 5/25/2017
Schedule
Service List
Service List, 5/4/2017
Hearing Program
Transcripts
Afternoon Evidentiary Transcript, 6/20/2017
Evening Evidentiary Transcript, 6/20/2017
Hearing Transcript Memorandum, 7/5/2017
PARTIES AND INTERVENORS
________________________________________________________________________________________________
APPLICANT - HOMELAND TOWERS LLC & CELLCO PARTNERSHIP d/b/a VERIZON WIRELESS
________________________________________________________________________________________________________________________________
Exhibits
Applicant's Responses to Council Interrogatories, 5/31/2017
Applicant's Sign Posting Affidavit, 6/6/2017
Applicant's Pre-Hearing Submission, 6/15/2017
Correspondence
Applicant's Letter to Pamela Westmoreland, 6/1/2017
Motions and Objections
Post Hearing Briefs and Draft Finding of Fact
________________________________________________________________________________________________
PARTY - PAMELA WESTMORELAND
________________________________________________________________________________________________________________________________
Correspondence
Council Approval of Pamela Westmoreland's Request for Party Status, 5/25/2017
Motions and Objections
Post Hearing Briefs and Draft Findings of Fact
DRAFT FINDINGS OF FACT
FINAL DECISION
Council's Decision Package, 09/15/17
DEVELOPMENT AND MANAGEMENT PLAN
Sabre Industries Structural Design Report, 10/19/17
Terracon Geotechnical Engineering Report, 09/29/17
Antenna Product Specifications
Diesel Generator Set Product Specifications
Commscope Drawing for Equipment Platform
Antenna Product Specifications
Antenna Product Specifications
Eastern Rack Layout for radios
D&M Plan Decision Letter, 12/22/17