DOCKET NO. 461A - Eversource Energy application for a Certificate of Environmental Compatibility and Public Need for the construction, maintenance, and operation of a 115-kilovolt (kV) bulk substation located at 290 Railroad Avenue, Greenwich, Connecticut, and two 115-kV transmission circuits extending approximately 2.3 miles between the proposed substation and the existing Cos Cob Substation, Greenwich, Connecticut, and related substation improvements. Reopening of this docket based on changed conditions pursuant to Connecticut General Statutes §4-181a(b).
Progress Report for January, 2020, 02/07/20
Progress Report for February, 2020, 03/05/20
Progress Report for March, 2020, 04/14/20
Progress Report for April, 2020, 05/07/20
Progress Report for May 2020, 06/09/20
Progress Report for June 2020, 07/14/20
Progress Report for July 2020, 08/19/20
Progress Report for August 2020, 09/03/20
Progress Report for September 2020, 10/13/20
Progress Report for October 2020, 11/10/20
Commencement of Operation Letter, 11/09/20
Construction Completion Letter, 11/24/20
Final Report, 05/27/21