DOCKET NO. 461A - Eversource Energy application for a Certificate of Environmental Compatibility and Public Need for the construction, maintenance, and operation of a 115-kilovolt (kV) bulk substation located at 290 Railroad Avenue, Greenwich, Connecticut, and two 115-kV transmission circuits extending approximately 2.3 miles between the proposed substation and the existing Cos Cob Substation, Greenwich, Connecticut, and related substation improvements. Reopening of this docket based on changed conditions pursuant to Connecticut General Statutes §4-181a(b).

 
 
Progress Reports
Monthly Progress Reports

 

Semi-Annual Status of Construction Reports

Commencement of Operation Letter, 11/09/20
Construction Completion Letter, 11/24/20
Final Report, 05/27/21