PETITION NO. 1444 - CP NB Solar I, LLC and CP NB Solar II, LLC petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a 1-megawatt AC solar photovoltaic electric generating facility and a 0.97-megawatt AC solar photovoltaic electric generating facility located at 127 Forest Road in North Branford, Connecticut, and associated electrical interconnection.

 

PETITON FILING (recd. 3/8/21)
Petition, 03/08/21

 

PROCEDURAL CORRESPONDENCE
Council Letter to the Town of North Branford, 03/09/21
Council State Agency Memorandum, 03/09/21
Council Incomplete Letter to Petitioner, 03/12/21
Council Acknowledgement of Petitioner Complete Submission, 03/15/21
Council Interrogatories to Petitioner, Set One, 04/16/21

 

STATE AGENCY COMMENTS
Council on Environmental Quality Comments, 03/25/21
Department of Agriculture Comments, 04/05/21

 

MUNICIPAL COMMENTS
Town of North Branford Comments, 02/26/21
Town of North Branford Additional Comments, received 05/21/21

 

SCHEDULE
Schedule, 03/09/21
Schedule, 03/12/21
Schedule, 03/16/21

 

SERVICE LIST
Service List, 03/09/21
Service List, 09/21/21

 

PETITIONERS -  CP NB Solar I, LLC and CP NB Solar II, LLC
Petitioner's Response to Council's Incomplete Letter, received 03/15/21
Petitioner's Supplemental Submission, 03/19/21
- GeoInsight Geotechnical Data Report 
- GeoInsight Investigation Summary Letter 
- GeoInsight Phase I Environmental Site Assessment Report 
Petitioner's Correction to Eastern Box Turtle Reference on Page 19 of Petition Narrative, 03/30/21
Petitioner Submission of Regional Water Authority Comments, 04/12/21
Petitioner Responses to Council Interrogatories, Set One, 04/29/21
Petitioner Supplemental Response to Council Interrogatories, Set One, No. 29, 05/27/21

DECISION
Council Decision and Staff Report, 06/04/21
Change of Control Letter of Altus Power, 09/17/21
Compliance Letter Condition No. 3 Submission, 09/17/21
Council Acknowledgement of Altus Power Change of Control Letter, 09/24/21
Council Acknowledgement of Condition No. 3 Submission, 09/24/21
Altus Submission of Decision Condition No. 2, 10/08/21
Attachment 1 - Solar Structural Calculations
Attachment 2 - Anchor Test Report
Council Acknowledgement of Condition No. 2 Submission, 10/21/21

DEVELOPMENT AND MANAGEMENT PLAN (D&M Plan)
D&M Plan Cover Letter, 10/08/21
D&M Site Plans 
Toxicity Characteristic Leaching Procedure Assessment Report
Council Decision (Denial) and Staff Report on Partial D&M Plan,  11/22/21
Revised D&M Plan, 11/24/21
Attachment 1 - Town of North Branford Letter
Attachment 2 - North Branford Farm and Trail Guide Brochure
Attachment 3 - Revised Spill Prevention, Control and Countermeasure Plan
D&M Plan Schedule, 11/26/21
Council Decision and Staff Report on Revised Partial D&M Plan, 12/17/21

Notice of Construction Commencement, 02/17/22