PETITION NO. 1225 – Eversource Energy petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed rebuilding and reconductoring of approximately two miles of its existing No. 1682 115-kV transmission line within existing right of way from the Wilton Substation at 53 Old Danbury Road, Wilton to Norwalk Junction at 111 Danbury Road, Wilton, Connecticut.
CORRESPONDENCE
DECISION