Open Certificate of Need applications
Below is a list of our current CON applications, you can view a full history of applications on the Certificate of Need portal.
Emergency Certificate of Need - the Emergency CON process differs from the standard CON process. Learn more here.
Applicant: Hartford HealthCare Corporation
Proposal: Transfer of ownership of a hospital licensed by DPH through bankruptcy proceedings
Docket number: 32843-ECON
Application date: 10/28/2025
Current status: OHS held a hearing on November 18, 2025. View the hearing.
Next steps: OHS will either issue a decision or agreed settlement.
Final decision due date: OHS - 12/30/2025
__________
Certificate of Need
Applicant: Bridgeport Hospital
Proposal: Acquisition of Linac and MR-Sim
Docket number: 32807
Application date: 5/6/2025
Current status: OHS has deemed the application complete.
Next steps: OHS will either hold a hearing or will issue a decision or agreed settlement.
Next due date: OHS - 12/24/2025
__________
Applicant: Norwalk Hospital
Proposal: Establishment of cardiac services
Docket number: 32808
Application date: 5/6/2025
Current status: OHS has closed the record.
Next steps: OHS to issue either a proposed final decision or an agreed settlement.
Next due date: OHS -1/27/2026
__________
Applicant: Emend Health Company LLC
Proposal: Establishment of a new health care facility
Docket number: 32783
Application date: 6/10/2025
Current status: OHS has deemed the application complete.
Next steps: OHS will either hold a hearing or will issue a decision or agreed settlement.
Next due date: Timeline suspended by mutual agreement of OHS and Applicant.
_______
Applicant: Paramount Operations BBD LLC d/b/d Paramount Wellness Centers
Proposal: Establishment of an outpatient behavioral health treatment center
Docket number: 32820
Application date: 7/10/2025
Current status: OHS has deemed the application complete.
Next steps: OHS will either hold a hearing or will issue a decision or agreed settlement.
Next due date: OHS-1/28/2026
_______
Applicant: Encompass Health Rehabilitation Hospital of Branford, LLC
Proposal: Establishment of a 50-bed chronic disease hospital
Docket number: 32826
Application date: 7/25/2025
Current status: OHS has deemed the application complete. The public now has 30 days to request a hearing (by 12/19/2025).
Next steps: OHS will either hold a hearing or will issue a decision or agreed settlement.
Next due date: OHS - 2/17/2026
_______
Applicant: CT Recovery Center, LLC
Proposal: Transfer of Ownership
Docket number: 32818
Application date: 8/19/2025
Current status: OHS has deemed the application complete. The public now has 30 days to request a hearing (by 12/14/2025).
Next steps: OHS will either hold a hearing or will issue a decision or agreed settlement.
Next due date: OHS - 2/12/2026
_______
Applicant: HHC Surgery/Surgical Center of CT/SCA-Main Street
Proposal: Transfer of Ownership
Docket number: 32834
Application date: 8/27/2025
Current status: OHS has deemed the application complete. The public now has 30 days to request a hearing (by 12/28)..
Next steps: OHS will either hold a hearing or will issue a decision or agreed settlement.
Next due date: OHS -2/26/2026
_______
Applicant: The Hospital of Central Connecticut
Proposal: Establishment of cardiac services.
Docket number: 32838
Application date: 9/29/2025
Current status: OHS issued a first completeness letter.
Next steps: Applicant to provide a response to first completeness letter.
Next due date: OHS - 12/28/2025
_____
Applicant: The Rowan Center d/b/a The Trauma Recovery Clinic at TRC
Proposal: Establishment of a behavioral health facility.
Docket number: 32805
Application date: 11/13/2025
OHS has deemed the application complete. The public now has 30 days to request a hearing (by 12/26)..
Next steps: OHS will either hold a hearing or will issue a decision or agreed settlement.
Next due date: OHS -2/24/2026
_____
Applicant: Project Bluegrass Holdco LLC
Proposal: Transfer of ownership.
Docket number: 32851
Application date: 11/14/2025
Current status: OHS issued a first completeness letter.
Next steps: Applicant to provide a response to first completeness letter.
Next due date: Applicant - 1/25/2026