CTDOT Construction Advisories

CTDOT Construction Advisories Header graphic

03/27/2023

Traffic Signal Safety and Technology Enhancements in Various CT Towns

The Connecticut Department of Transportation (CTDOT) is announcing traffic signal safety and technology enhancements will commence on April 3, 2023.

 

This project will remove the programmed flashing operation, installing 360-degree stop bar detection cameras and added dilemma zone detection radar units at 35 state-owned traffic control signals in southwestern Connecticut. Six locations that have exclusive pedestrian phases will have the non-countdown indications replaced with countdown pedestrian indications. At locations that do not currently have arterial detection, video or other type of detection will be installed on the arterial approaches. All existing traffic signal equipment will remain except the 6 locations that will have the non-countdown pedestrian indications replaced.

 

DOT Project No. 0173-0500 was awarded to The NY Conn Corp, Inc. at a cost of $2,062,472.00 November 3, 2022, and is scheduled to be completed on October 20, 2023.  This project is administered by the Bureau of Engineering and Construction, Office of Construction, District 3 in New Haven.

 

LANE CLOSURE INFO

There will be intermittent lane closures Monday through Friday between 9: a.m. and 3:00 p.m. and between 6:00 p.m. and 6:00 a.m. Some intersections and side roads allow intermittent lane closures Saturday and Sunday between 6:00 p.m. and 10:00 a.m.

 

Permitted closures during active work periods may restrict traffic to alternating one way traffic, with active traffic control, police or flagging personal.

 

Intersection improvements including traffic shifts and lane closures at the following intersections:

 

BETHANY

R0UTE 63 AT ROUTE 42 (CHESHIRE RD)

 

BRANFORD

ROUTE 146 AT KIRKHAM ST & MONROE ST

ROUTE 139 AT SCHOOL GROUND RD

 

EAST HAVEN

ROUTE 100 AT MILL ST

 

GUILDFORD

U.S. ROUTE 1 AT GUILFORD COMMONS DR

 

MADISON

SSR 450 AT GREEN HILL RD

SSR 450 AT I-95 NB RAMPS

ROUTE 79 AT I-95 SB RAMPS & DR TO OFFICE PARK

 

MILFORD

ROUTE 162 AT OLD GATE LN

 

NEW HAVEN

ROUTE 10 AT I-95 SB RAMPS

ROUTE 337 AT UPSON TERR

 

NORTH BRANFORD

ROUTE 22 AT VILLAGE ST #1 & VILLAGE ST #2

ROUTE 80 AT BIG Y DR

 

NORTH HAVEN

U.S. ROUTE 5 AT SACKETT POINT RD

U.S. ROUTE 5 AT SR 717 (DIXWELL AVE) & STILES LN

ROUTE 22 AT POOL RD

ROUTE 22 AT BASSETT RD AND MILL RD

SR 717 AT RTE 40 SB RAMPS & HARTFORD TPKE

SR 729 (BROADWAY) AT ELM ST

U.S. ROUTE 5 AT SKIFF ST

U.S. ROUTE 5 AT SR 720 (DEVINE ST) & DEVINE ST

SR 715 (MONTOWESE AVE) AT I-91 RAMPS & FRONTAGE RD

SR 717 (DIXWELL AVE) AT ROUTE 15 NB RAMPS & VISTA RD

U.S. ROUTE 5 AT NORTH HAVEN PLAZA DR

 

WEST HAVEN

SR 705 (OCEAN AVE) AT SOUTH ST

SR 705 (OCEAN AVE/PLATT CT) AT OCEAN AVE #1 & PARKING LOT DR

ROUTE 34 AT CENTRAL AVE

ROUTE 162 AT SOUTH ST

 

WOODBRIDGE

ROUTE 63 AT ROUTE 114 (CENTER RD)


FOR MORE INFORMATION:
860-594-2560
DOT.CustomerCare@ct.gov
Operating Hours: Monday - Friday 8:00 a.m. to 4:30 p.m.

 

Share this information on: