Pavement Marking Project on Route 9 Southbound in New Britain

UPDATE 2/9/2023: This project has been postponed until further notice.

The Connecticut Department of Transportation (CTDOT) is announcing that a Pavement Marking Project will be performed on Route 9 southbound Exit 25 in New Britain on Friday February 10, 2023.

The project(#  DOT0170-3638CN) consists of installing safety marking reflectors on the Route 9 southbound Exit 25 off-ramp as part of ongoing wrong way driver mitigation measures. This project is being performed by Safety Marking with the assistance of State forces. Work will occur on Friday February 10, 2023.

RAMP CLOSURE INFO/DETOUR INFO

Motorists can expect exit 25 on Route 9 southbound to be closed in New Britain for a duration of two hours while the work is being performed. Traffic control personnel and signing patterns will be utilized to alert motorists.

Motorists will have to continue to Exit 23 (Christian Lane) taking a left at the end of the ramp to redirect to Route 9 northbound. Work schedule for this project is between the hours of 7:00 a.m. to 4:00 p.m.