The Connecticut Department of Transportation (CTDOT) is announcing that milling and resurfacing project will be performed on Route 47 in Washington, from Route 109 to Route 202.
The project consists of milling and resurfacing a 3.10 mile of Route 47 Washington. The milling of this project is scheduled to start on Monday, June 6, 2022 and end on Tuesday, June 7, 2022. The resurfacing of this project is scheduled to start on Monday, June 13, 2022 and be completed on Tuesday, June 21, 2022.
This project is included in the Department of Transportation’s 2022 Vendor Resurfacing Program.
LANE CLOSURE INFO
Motorists can expect delays and one lane alternating Traffic. The regular work schedule for this project is Monday – Friday from 7 a.m. to 4 p.m. Traffic control personnel and signing patterns will be utilized to guide motorists through the work zone.
The information below must be filled in for press information to show up on map and website
Specific Date e-alert to be issued: May 26, 2022