The project consists of the rehabilitation of Bridge Nos. 01708 and 03374, Route 2 over West Road. The lane closures will be implemented to facilitate the repair of the deteriorated deck ends and to replace the existing asphaltic plug joints.
DOT Project No. 0078-0092 was awarded to McNamee Construction Corp., of Oxford, CT, at a cost of $2,114,000.00 on November 20, 2020 and is scheduled to be completed in December of 2021. This project is administered by the Office of Construction, District 2 in Norwich.
LANE CLOSURE INFORMATION
Weekend 1: 10/15 – 10/18
Route 2 Eastbound:
8 PM, October 15, 2021 until 8 AM, October 18, 2021
Route 2 Westbound:
7 PM, October 15, 2021 until 6 AM, October 18, 2021
Weekend 2: 10/22 – 10/25
Route 2 Eastbound:
8 PM, October 22, 2021 until 8 AM, October 25, 2021
Route 2 Westbound:
7 PM, October 22, 2021 until 6 AM, October 25, 2021
Weekend 3: 10/29 – 11/01
Route 2 Eastbound:
8 PM, October 29, 2021 until 8 AM, November 1, 2021
Route 2 Westbound:
7 PM, October 29, 2021 until 6 AM, November 1, 2021