Rehabilitation of Bridge 00032 Carrying I-95 over Metro North Railroad and Local Roads in Stamford

The Connecticut Department of Transportation is announcing lane and ramp closures to facilitate work activity for the the project to rehabilitate Bridge 00032 which carries I-95 over Metro North Railroad and local roads in Stamford.

 

The contractor will be closing the I-95 northbound Exit 7 on-ramp from Elm Street, through November 6, 2020, from 8:00 PM to 6:00 AM, Monday through Friday.

 

The contractor will be allowed lane closures on I-95 between Exit 7 and Exit 8 through December 1, 2020, as follows:

 

Interstate 95 northbound:

  • Monday – Wednesday between 7:00 p.m. and 5:00 a.m.
  • Thursday between 8:00 p.m. and 5:00 a.m.
  • Friday between 9:00 p.m. and 5:00 a.m.
  • Saturday between 6:00 p.m. and 6:00 a.m.
  • Sunday between 6:00 p.m. and 9:00 a.m.

Interstate 95 southbound: 

  • Monday – Friday between 6:00 p.m. and 5:00 a.m.
  • Saturday between 6:00 p.m. and 7:00 a.m.
  • Sunday between 6:00 p.m. and 8:00 a.m.

The project consists of repairs to structural bridge components, deck patching, deck end repairs,  expansion joint replacement, structural steel repairs and  substructure repairs

 

DOT Project No. 0135-0334 was awarded to ROTHA Contracting Co. at a cost of $ 16,990,206.95, on November 4, 2020, and is scheduled to be completed October 1, 2021.