CONNECTICUT DEPARTMENT OF TRANSPORTATION
NEWS RELEASE
2800 BERLIN TURNPIKE P.O. BOX 317546
NEWINGTON CONNECTICUT, 06131-7546
FOR RELEASE: April 23, 2018
FOR FURTHER INFORMATION:
OFFICE OF COMMUNICATIONS
TELEPHONE: (860) 594-3062
FAX: (860) 594-3065
WEB SITE: www.ct.gov/dot

New Haven-Hartford-Springfield (NHHS) Rail Program

Construction Update: Town of Windsor

(Railroad Crossing Work: Paving Schedule – Weekday/Daytime Work)

April 30 – May 4, 2018

Beginning Monday, April 30th and concluding by Friday, May 4th, there will be surface milling and final paving work at various railroad crossings in Windsor. This will require one-way traffic and/or road closures and will occur daily during the hours of 6:00 a.m. – 5:00 p.m.

This work will occur at the Meadow Road, East Barber Street, Island Road and Central Street railroad crossings.

Traffic personnel will be in place throughout the duration of the detours/closures. Signs, variable message boards and detour routes alerting the public of the detour/closure will be posted on-site.

Please note that this schedule is subject to change.

For construction related questions, please contact Rob Canestra, Project Engineer, AECOM at (860) 924-8809 or Rich Angelicola, Resident Engineer, AECOM at (860) 867-6460. For Amtrak service schedule information please visit www.amtrak.com or call 1(800) 872-7245.

This work is part of the overall upgrade of the New Haven-Hartford-Springfield rail line –branded as the CTrail Hartford Line – scheduled to begin expanded service in June 2018.

Future updates on the status and location of construction activities will be provided on the NHHS Rail Program website at www.nhhsrail.com, Facebook, Twitter and by email. To receive email updates, please register on the NHHS Rail Program website.