CONSTRUCTION BI-WEEKLY PROJECT UPDATE: Weeks of 06/19/2023 - 06/30/2023

Night Work

I-691 - on the Lewis Avenue, Notch Road, and Hubbard Park Bridges

  • concrete patch repairs
  • catch basin and ramps.
  • sign installation
  • guard rail installation
  • surveying and markings

At Columbia Avenue

  • demolishing and reconstructing end blocks
  • milling and pavement restoration
  • demolishing backwall and installing rebar.

Center Street, Bunker Street, Broad Street, Colony Street Bridges

  • paving

At Notch Road, Bunker Street and Broad Street bridges

  • installing plug joints
  • guano abatement

 

Day Work

All along project limits at I-691

  • sign installation
  • surface mount installation 

Columbia Avenue

  • concrete pour for the new backwall

 

TRAFFIC IMPACTS: One or two lanes along I-691 will be closed to traffic from 6 PM to 7 AM. All lanes will be reopened and operational during peak traffic hours.

CONSTRUCTION BI-WEEKLY PROJECT UPDATE: Weeks of 8/22/2022 -9/2/2022

Day time - I-691 EB and WB 

gif

Crews will be demolishing and reconstructing I-691 Eastbound end blocks outside of the roadway from 7 AM to 6 PM

Crews will install cables in ducts along I-691 Eastbound. Crews will also trench and backfill in Stages 3 and 4 of I-691 Eastbound. 

Local Roads

gif

No anticipated day time activities. 

 

Night work:

gif

I-691 EB & WB – Night Time

August 22 through September 9, during the nighttime hours, between 7 PM and 6 AM, crews will conduct roadway patching along the I-691 Eastbound bridges. Crews will be removing and replacing existing concrete pavement repairs on Stages 1 and 2 and the ramps of I-691 Westbound. Crews will also be surveying patches and bridge deck elevations. Work on electrical light pole bases will continue along I-691 Eastbound and then move to I-691 Westbound during the week of August 29.  

From August 22 to September 2, during the nighttime hours, crews will be saw cutting for concrete pavement repairs in Stages 2 and 3 of I-691 Westbound. Crews will also be removing curbing along I-691 Eastbound and cleaning trenches along the bridges of I-691 Eastbound.  

The week of September 6 through September 9, during nighttime hours, crews will lay the binder course along Stage of I-691 Eastbound. Crews will also be milling Stage 3 and ramps of I-691 Westbound. 

 

TRAFFIC IMPACTS:

Work will be conducted primarily during nighttime hours, from 7 PM to 6 AM. One or two lanes along I-691 will be closed to traffic while nighttime work is underway. All lanes will be reopened and operational during peak traffic hours.