Project 0079-0244 Construction Alerts Page
Project Home
Construction Alerts - Sign up for CTroads
Progress & Photos
Feedback - Register for Alerts
CONSTRUCTION BI-WEEKLY PROJECT UPDATE: Weeks of 06/19/2023 - 06/30/2023
Night Work
I-691 - on the Lewis Avenue, Notch Road, and Hubbard Park Bridges
- concrete patch repairs
- catch basin and ramps.
- sign installation
- guard rail installation
- surveying and markings
At Columbia Avenue
- demolishing and reconstructing end blocks
- milling and pavement restoration
- demolishing backwall and installing rebar.
Center Street, Bunker Street, Broad Street, Colony Street Bridges
- paving
At Notch Road, Bunker Street and Broad Street bridges
- installing plug joints
- guano abatement
Day Work
All along project limits at I-691
- sign installation
- surface mount installation
Columbia Avenue
- concrete pour for the new backwall
TRAFFIC IMPACTS: One or two lanes along I-691 will be closed to traffic from 6 PM to 7 AM. All lanes will be reopened and operational during peak traffic hours.
CONSTRUCTION BI-WEEKLY PROJECT UPDATE: Weeks of 8/22/2022 -9/2/2022
I-691 East and Westbound - Day Time
Crews will be demolishing and reconstructing I-691 Eastbound end blocks outside of the roadway from 7 AM to 6 PM
Crews will install cables in ducts along I-691 Eastbound. Crews will also trench and backfill in Stages 3 and 4 of I-691 Eastbound.
Local Roads
No anticipated day time activities.
I-691 East and Westbound – Night Time
August 22 through September 9, during the nighttime hours, between 7 PM and 6 AM, crews will conduct roadway patching along the I-691 Eastbound bridges. Crews will be removing and replacing existing concrete pavement repairs on Stages 1 and 2 and the ramps of I-691 Westbound. Crews will also be surveying patches and bridge deck elevations. Work on electrical light pole bases will continue along I-691 Eastbound and then move to I-691 Westbound during the week of August 29.
From August 22 to September 2, during the nighttime hours, crews will be saw cutting for concrete pavement repairs in Stages 2 and 3 of I-691 Westbound. Crews will also be removing curbing along I-691 Eastbound and cleaning trenches along the bridges of I-691 Eastbound.
The week of September 6 through September 9, during nighttime hours, crews will lay the binder course along Stage of I-691 Eastbound. Crews will also be milling Stage 3 and ramps of I-691 Westbound.
TRAFFIC IMPACTS
Work will be conducted primarily during nighttime hours, from 7 PM to 6 AM. One or two lanes along I-691 will be closed to traffic while nighttime work is underway. All lanes will be reopened and operational during peak traffic hours.
ARCHIVED CONSTRUCTION ALERTS