Due to the personally identifying information contained in written limited appearance statements from the public, any written limited appearance statements that are received by the Council for any matter are available to be viewed at the Council’s office Monday through Friday from 8:30 a.m. to 4:30 p.m. or available to be sent via e-mail upon request. Please allow adequate time for processing.

Long Island Sound Resource and Use Inventory/Long Island Sound Blue Plan Survey

Petition No. 1679 - Eversource Energy - Scoville Rock Switching Station to East of Hurd State Park Rebuild Project

PETITION NO. 1679 – The Connecticut Light and Power Company d/b/a Eversource Energy petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the Scovill Rock Switching Station to East of Hurd State Park Rebuild Project consisting of the replacement and reconductoring of electric transmission line structures along approximately 2.4 miles of its existing 115-kilovolt (kV) 1772 Line and 345-kV 376 and 362 Lines shared right-of-way and associated Connecticut River Crossing between Scovill Rock Switching Station in Middletown and Structure 19098 in Haddam traversing the municipalities of Middletown, East Hampton, and Haddam, Connecticut, and related electric transmission line and substation improvements.

 

PETITION (recd. 07/15/25)
Petition Filing, 07/15/25

 

PROCEDURAL CORRESPONDENCE
Council Letter to City of Middletown, 07/17/25
Council Letter to Town of East Hampton, 07/17/25
Council Letter to Town of Haddam, 07/17/25
Council Set Date for Decision, 08/22/25
Council Interrogatories to Petitioner, 10/28/25

 

STATE AGENCY COMMENTS
Council on Environmental Quality, 07/24/25

 

SCHEDULE
Schedule, 07/16/25
Schedule, 08/21/25
Schedule, 10/28/25

 

SERVICE LIST  
Service List, 07/15/25

 

PETITIONER - The Connecticut Light and Power Company d/b/a Eversource Energy
Responses to Council Interrogatories, 11/18/25