PETITION NO. 1475 – The Connecticut Light and Power Company d/b/a Eversource Energy petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed Eastern Connecticut Reliability Project consisting of the replacement and reconductoring of electric transmission line structures along approximately 2.1 miles of its existing Nos. 100 and 400 69-kilovolt (kV) and Nos. 1410 and 1280 115-kV electric transmission lines within existing Eversource electric transmission line right-of-way between Montville Junction, Montville and Ledyard Junction, Ledyard, Connecticut, and related electric transmission line and substation improvements.
PETITION (recd. 12/28/21)
PROCEDURAL CORRESPONDENCE
Council Letter to the Town of Ledyard, 12/30/21
Council Letter to the Town of Montville, 12/30/21
Council Interrogatories to Petitioner, Set One, 01/20/22
Eversource Request for Extension to Respond to Interrogatories and Council Approval, 01/28/22
STATE AGENCY COMMENTS
MUNICIPAL COMMENTS
SCHEDULE
Schedule, 12/30/21
Schedule, 01/20/22
SERVICE LIST
Service List, 12/29/21
PETITIONER - The Connecticut Light and Power Company d/b/a Eversource Energy (Eversource)
Eversource Responses to Interrogatories, Set One, 02/03/22
DECISION
Council Decision and Staff Report, 02/25/22
Request for Revision of Work Hours and Council Decision, 09/08/22
Notice of Completion, 09/01/23