Due to the personally identifying information contained in written limited appearance statements from the public, any written limited appearance statements that are received by the Council for any matter are available to be viewed at the Council’s office Monday through Friday from 8:30 a.m. to 4:30 p.m. or available to be sent via e-mail upon request. Please allow adequate time for processing.

Please be advised that the Connecticut Siting Council will not be accepting any hard copy filings for any matter after 12 PM on Wednesday, December 24, 2025. Regular file processing will resume at 8:30 AM on Friday, December 26, 2025. Thank you for your consideration.

PETITION NO. 1402 - Bloom Energy Corporation petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a 350-kilowatt customer-side fuel cell facility and associated equipment located at Western Connecticut State University, 7 University Boulevard, Danbury, Connecticut.


PETITION

Petition (received 04/17/20)


PROCEDURAL CORRESPONDENCE

Council Letter to the City of Danbury, 04/20/20
State Agency Comment Memorandum, 04/20/20
Council Interrogatories to Bloom Energy Corporation, Set One, 04/28/20
Council Interrogatories to Bloom Energy Corporation, Set Two, 04/30/20


STATE AGENCY COMMENTS
Department of Transportation Comments, 06/10/20 


SCHEDULE
Schedule, 4/20/20


SERVICE LIST
Service List, 04/17/20

PETITIONER-BLOOM ENERGY CORPORATION
Petitioner's Responses to Council Set One Interrogatories, Set One, 5/6/20
Petitioner's Responses to Council Set Two Interrogatories, Set Two, 5/6/20


DECISION
Council Decision and Staff Report, 05/22/20

Council Status Update Letter, 11/15/24
Notice of Construction Completion, 12/13/24