PETITION NO. 1343 – The Connecticut Light and Power Company d/b/a Eversource Energy petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed PSEG Bridgeport Harbor Unit 5 Line Reconductoring Project consisting of conductor replacements on its existing No. 1670 115-kilovolt (kV) electric transmission line extending approximately 5.2 miles within existing Eversource electric transmission line right-of-way between the Southington Substation located at Belleview Avenue in Southington, Connecticut and Reservoir Junction located at Reservoir Road in New Britain, Connecticut, and related substation and electric transmission line structure improvements.
PETITION
Petition Filing (received 4/18/2018)
PROCEDURAL CORRESPONDENCE
DECISION