PETITION NO. 1278B - Bloom Energy Corporation, as an agent for Medtronic Inc., second request to amend to its declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, operation and maintenance of an additional customer-side 2,000-kilowatt fuel cell facility to be located at the Medtronic campus, 195 McDermott Road, North Haven, Connecticut. Petition No. 1278 Petition No. 1278A
AMENDED PETITION (recd. 08/07/23)
Petition Filing, 08/04/23
PROCEDURAL CORRESPONDENCE
Council Letter to Town of North Haven, 08/09/23
Council Letter to Town of East Haven, 08/09/23
Council Letter to Town of New Haven, 08/09/23
Council State Agency Comment Memorandum, 08/09/23
Council Interrogatories to Petitioner, Set One, 08/28/23
Council Set Date for Decision, 09/28/23
STATE AGENCY COMMENTS
Connecticut Airport Authority Comments, 08/16/23
MUNICIPAL COMMENTS
SCHEDULE
Schedule, 08/07/23
Schedule, 08/28/23
Schedule, 09/28/23
SERVICE LIST
Service List, 08/08/23
PETITIONER - Bloom Energy Corporation
Petitioner Responses to Council Interrogatories, Set One, 09/12/23
Federal Aviation Administration Determination of No Hazard to Air Navigation for Temporary Structure, 10/03/23
Federal Aviation Administration Determination of No Hazard to Air Navigation, 10/03/23