Docket No. 551 - Homeland Towers, LLC and Cellco Partnership d/b/a Verizon Wireless - Telecommunications Facility - 402 Clintonville Road, North Haven
DOCKET NO. 551 - Homeland Towers, LLC and Cellco Partnership d/b/a Verizon Wireless application for a Certificate of Environmental Compatibility and Public Need for the construction, maintenance, and operation of a telecommunications facility and associated equipment located at 402 Clintonville Road, North Haven, Connecticut.
APPLICATION (recd. 04/14/26)
Attachments:
1. Site Evaluation Report and Project Plans
2. Certificate of Service of Application on Government Officials and List of Officials Served
3. Legal Notice in the New Haven Register
4. Notice to and List of Abutting Landowners; Certificate of Service
5. Federal Communications Commission Licenses - Cellco Partnership d/b/a Verizon Wireless
6. Coverage Maps – Surrounding Cell Sites
7. Antenna, Equipment and Generator Specifications
8. Site Search Summary
9. Visual Resources Assessment
10. USFWS/NDDB Compliance
11. Wetlands Assessment Report
12. State Historic Preservation Determination
13. Farmland Classification Map
14. Far Field RF Emissions Calculation
15. National Flood Hazard Layer Map - FIRMette
16. FAA Opinion Letter
17. Redacted Option and Ground Lease Agreement
Bulk:
1. Technical Report
2. Town of North Haven Zoning Regulations
3. Town of North Haven Inland Wetlands and Watercourses Regulations
4. Town of North Haven Plan of Conservation and Development
PROCEDURAL CORRESPONDENCE
Council Letter to the Town of North Haven, 04/15/26
Council Completeness Review and Schedule, 04/30/26
Council Interrogatories to Applicants, 06/12/26
Council Decision on Motion for Protective Order, 07/16/26
Council Close of Record Memorandum, 07/16/26
STATE AGENCY COMMENTS
State Historic Preservation Office Comments, 06/05/26
MUNICIPAL COMMENTS
Town of North Haven Fire Department Comments, 07/16/26
PUBLIC OFFICIAL COMMENTS
State Senator Paul Cicarella Comments, 04/16/26
HEARING INFORMATION
July 16, 2026 Hearing Documents, 05/01/26
1. Instructions to Public Access to Remote Public Hearing
2. Hearing Notice
3. Hearing Program
4. Citizens Guide to Siting Council Procedures; and
5. Proposed Facility Site Plan
Hearing Procedures and Pre-Hearing Conference Memorandum, 06/03/26
Zoom Remote Public Hearing Recording, 07/16/26 (Passcode: ^#8X=gZ$ )
SCHEDULE
Schedule, 04/15/26
Schedule, 04/30/26
Schedule, 06/12/26
Schedule, 07/16/26
Schedule, 07/24/26
SERVICE LIST
HEARING PROGRAM
TRANSCRIPT
Evidentiary Hearing Transcript 2 p.m., 07/16/26
Public Comment Session Transcript 6:30 p.m., 07/16/26
Council Transcript Memorandum, 08/04/26
Applicants - Homeland Towers, LLC and Cellco Partnership d/b/a Verizon Wireless
Exhibits
Affidavit of Publication in the New Haven Register, 04/30/26
Responses to Council Interrogatories, 07/01/26
Sign-Posting Affidavit, 07/07/26
Signed Protective Order - Lease Agreement Financial Terms, 07/16/26
Procedural Correspondence
Pre-Hearing Submission, 07/09/26/
Consent to Council's Deadline Extension Request, 07/24/26
Motions and Objections
Motion for Protective Order - Lease Agreement Financial Terms, 04/22/26
Briefs/Proposed Findings of Fact
Letter in Lieu of Post-Hearing Brief, 08/12/26
COUNCIL'S DRAFT FINDINGS OF FACT
FINAL DECISION