Docket No 527
DOCKET NO. 527 – Windham Energy Center, LLC application for a Certificate of Environmental Compatibility and Public Need for the construction, maintenance, and operation of a 325-megawatt battery energy storage facility and associated equipment located at 189 Lake Road, Killingly, Connecticut, and associated electrical interconnection.
APPLICATION (recd. 10/11/24)
Narrative, 10/11/24
Figures
A. Notice Requirements
B. Statement of Need and Economic Benefits
C. Documentation Associated with Cancellation of NTE Project
D. Project Site Plans
E. BESS Vendor Specifications
F. BESS Safety Procedures
G. Preliminary Windham Energy Center Operation & Maintenance Plan
H. Geotechnical Report
I. Stormwater Analysis/SWPPP
J. Delineation Report
K. Ecological Assessment
L. Species Correspondence
M. Acoustic Assessment
N. EMF Report
O. Cultural Resource Correspondence
Bulk Filings:
Technical Report
Town of Killingly Zoning Regulations
Town of Killingly Inland Wetlands and Watercourses Regulations
Town of Killingly Plan of Conservation and Development
PROCEDURAL CORRESPONDENCE
Council's Municipal Participation Fund Letter, 10/16/24
Council's Incomplete Notice, 10/21/24
Council's Acknowledgement of Complete Application, 10/23/24
Council Completion Review, 11/07/24
Council's Notice of Incomplete Application, 11/08/24
Council Acknowledgement of the Town of Killingly's Request for Party Status, 11/22/24
Request for Extension of Time to Submit Hard Copies of Municipal Orders and Council Extension Decision, 12/16/24
Council Decision on Applicant's Request for an Extension of Time to Respond to Notice of Incomplete Application, 12/18/24
STATE AGENCY COMMENTS
MUNICIPAL COMMENTS
PUBLIC OFFICIAL COMMENTS
HEARING INFORMATION
Schedule
Schedule, 10/11/24
Schedule, 10/21/24
Schedule, 10/23/24
Schedule, 11/08/24
Service List
Service List, 10/11/24
Hearing Program
Transcripts
PARTIES AND INTERVENORS
Applicant - Windham Energy Center, LLC
Exhibits
Applicant's Affidavit of Publication, 10/18/24
Applicant's Supplemental Certification of Service, 10/23/24
Procedural Correspondence
Applicant's Response to Council's Notice of Incomplete Application, 11/21/24
Applicant's Request for an Extension of Time to Respond to Notice of Incomplete Application, 12/17/24
Motions and Objections
Post-Hearing Brief and Draft Findings of Fact
Party - Town of Killingly (Town) - pending
Town Request for Party Status, 11/22/24
Town Inland Wetlands and Watercourses Commission Order to Regulate and Restrict and Planning and Zoning Commission Order of Regulations and Restrictions, 12/16/24