Docket No 527

DOCKET NO. 527 – Windham Energy Center, LLC application for a Certificate of Environmental Compatibility and Public Need for the construction, maintenance, and operation of a 325-megawatt battery energy storage facility and associated equipment located at 189 Lake Road, Killingly, Connecticut, and associated electrical interconnection.

APPLICATION (recd. 10/11/24)
Narrative, 10/11/24
Figures
A.  Notice Requirements
B.  Statement of Need and Economic Benefits
C.  Documentation Associated with Cancellation of NTE Project
D.  Project Site Plans
E.  BESS Vendor Specifications
F.  BESS Safety Procedures
G.  Preliminary Windham Energy Center Operation & Maintenance Plan
H.  Geotechnical Report
I.  Stormwater Analysis/SWPPP
J.  Delineation Report
K.  Ecological Assessment
L.  Species Correspondence
M.  Acoustic Assessment
N.  EMF Report
O.  Cultural Resource Correspondence

Bulk Filings:
Technical Report
Town of Killingly Zoning Regulations
Town of Killingly Inland Wetlands and Watercourses Regulations
Town of Killingly Plan of Conservation and Development

 

PROCEDURAL CORRESPONDENCE
Council's Municipal Participation Fund Letter, 10/16/24
Council's Incomplete Notice, 10/21/24
Council's Acknowledgement of Complete Application, 10/23/24
Council Completion Review, 11/07/24
Council's Notice of Incomplete Application, 11/08/24
Council Acknowledgement of the Town of Killingly's Request for Party Status, 11/22/24
Request for Extension of Time to Submit Hard Copies of Municipal Orders and Council Extension Decision, 12/16/24
Council Decision on Applicant's Request for an Extension of Time to Respond to Notice of Incomplete Application, 12/18/24

 

STATE AGENCY COMMENTS

 

MUNICIPAL COMMENTS

 

PUBLIC OFFICIAL COMMENTS

 

HEARING INFORMATION

 

Schedule
Schedule, 10/11/24
Schedule, 10/21/24
Schedule, 10/23/24
Schedule, 11/08/24

 

Service List
Service List, 10/11/24

 

Hearing Program

 

Transcripts

 

PARTIES AND INTERVENORS

Applicant - Windham Energy Center, LLC 
Exhibits
Applicant's Affidavit of Publication, 10/18/24
Applicant's Supplemental Certification of Service, 10/23/24

 

Procedural Correspondence
Applicant's Response to Council's Notice of Incomplete Application, 11/21/24
Applicant's Request for an Extension of Time to Respond to Notice of Incomplete Application, 12/17/24

 

Motions and Objections

 

Post-Hearing Brief and Draft Findings of Fact

 

Party - Town of Killingly (Town) - pending
Town Request for Party Status, 11/22/24
Town Inland Wetlands and Watercourses Commission Order to Regulate and Restrict and Planning and Zoning Commission Order of Regulations and Restrictions, 12/16/24