PETITION NO. 1575 – The Connecticut Light and Power Company d/b/a Eversource Energy petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for proposed modifications to its existing Salisbury Substation located at 316 Indian Mountain Road, Salisbury, Connecticut, and related electric transmission line structure improvements.


PETITION (recd. 05/22/23)

Petition Filing, 05/18/23

 

PROCEDURAL CORRESPONDENCE
Council Letter to Town of Salisbury, 05/23/23
Council Interrogatories to Petitioner, Set One, 06/20/23
Council Set Date for Decision, 07/20/23

 

MUNICIPAL COMMENT

 

SCHEDULE
Schedule, 05/22/23
Schedule, 06/20/23
Schedule, 07/20/23

 

SERVICE LIST
Service List, 05/23/23

 

PETITIONER - The Connecticut Light and Power Company d/b/a Eversource Energy
Petitioner's Responses to Council Interrogatories, Set One, 07/10/23

 

 

DECISION
Council Decision and Staff Report, 09/01/23
Notice of Construction Commencement, 09/11/23
Council Acknowledgement of Declaratory Ruling Condition Nos. 2 and 4 Submission, 09/11/23
Petitioner's Request for Project Change and Council Decision, 11/16/23
Request for Temporary Extended Work Hours, 03/14/24
Request for Temporary Extended Work Hours and Council Decision, 08/15/24
Request for Temporary Extended Work Hours and Council Decision, 08/20/24