PETITON NO. 1533
 – ReNew Developers, LLC petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a customer-side 4.99-megawatt fuel cell facility and associated equipment to be located at 42 Old Amston Road, Colchester, Connecticut.

 

PETITION (recd. 07/29/22)
Petition Filing, 07/28/22
Exhibit A: Site Plan and Site Photographs
Exhibit B: Bloom Energy Server 5 Equipment Specification Sheet
Exhibit C: Public Notice Documentation (Service Lists, Sample Notice Letters, Affidavits and Abutters Map)
Exhibit D: Other Correspondence - Letter dated May 15, 2022 from CMMD, LLC to the Siting Council, Letter dated May 14, 2022 from First Selectman Bisbikos to the Council
Exhibit E: Environmental Assessment
Exhibit F: Stormwater Management Report 
Exhibit G: Facility Sound Assessment
Exhibit H: Preliminary Archaeological Assessment (including SHPO Correspondence) 
Exhibit I: FEMA Flood Maps
Exhibit J: NDDB Correspondence and USFWS Compliance Statement 
Exhibit K: Emergency Response Plan

 

PROCEDURAL CORRESPONDENCE
Council Letter to the Town of Colchester, 08/01/22
Council Letter to the Town of Hebron, 08/01/22
Council State Agency Comment Memorandum, 08/01/22
Council Interrogatories to Petitioner, Set One, 08/25/22
Council Set Date for Decision, 09/15/22

MUNICIPAL COMMENTS

 

STATE AGENCY COMMENTS
Council on Environmental Quality Comments, 08/25/22
Department of Energy & Environmental Protection Comments, 08/31/22

 

SCHEDULE
Schedule, 07/29/22
Schedule, 08/25/22
Schedule, 09/15/22

 

SERVICE LIST
Service List, 08/01/22

 

PETITIONER - ReNew Developers, LLC (ReNew)
ReNew Responses to Council Interrogatories, Set One, 09/09/22

 

DECISION
Council Decision and Staff Report, 10/14/22