• For any person seeking access to the Council's records, please email siting.council@ct.gov at least 24 hours in advance for an appointment.

DOCKET NO. 515 - Cellco Partnership d/b/a Verizon Wireless application for a Certificate of Environmental Compatibility and Public Need for the construction, maintenance, and operation of a telecommunications facility located east of the Student Transportation Parking Lot at 180 School Road, Wilton, Connecticut.

APPLICATION (recd. 03/17/23)
Narrative, 03/17/23

LIST OF ATTACHMENTS
1.  Wilton South Facility- Factual Summary and Project Plans
2.  Certificate of Service of Application on Government Officials; and List of Officials Served
3.  Legal Notice in the The Hour
4.  List of Abutting Landowners and Certificate of Service; Notice Letter
5.  Federal Communications Commission Licenses
6.  Coverage Maps -Location of Wilton South and Surrounding Cell Sites
7.  Antenna and Equipment Specifications
8.  Visibility Analysis
9.  USFWS and NDDB Compliance Determination
10. Wetlands Inspection Report
11. Preliminary Historic Resources Determination
12. Farmland Soils Map
13. Maximum Permissible Exposure -Far Field Calculation
14. National Flood Hazard Layer FIRMette
15. Town of Wilton Waiver - 90-day Municipal Consultation
16. Federal Airways & Airspace Summary Report 
17. Land Lease Agreement - Redacted

BULK
Town of Wilton Zoning Regulations
Town of Wilton Inland Wetlands and Watercourses Regulations
Town of Wilton Plan of Conservation and Development

 

PROCEDURAL CORRESPONDENCE
Council Letter to Town of Wilton, 03/20/23
Council Completeness Review, 04/13/23
Council Interrogatories to Applicant, Set One, 04/28/23

 

STATE AGENCY COMMENTS
Connecticut Airport Authority Comments, 04/17/23

 

MUNICIPAL COMMENTS

 

PUBLIC OFFICIAL COMMENTS

 

TELECOMMUNICATIONS CARRIER CORRESPONDENCE

 

HEARING INFORMATION
June 29, 2023 Hearing Documents, 04/13/23
1.  Instruction for Public Access to Remote Public Hearing
2.  Public Hearing Notice
3.  Hearing Program (currently not available)
4. Citizens Guide to Siting Council Procedures; and
5.  Proposed Facility Site Plan (currently not available)

 

Schedule
Schedule, 03/17/23
Schedule, 04/13/23

Service List 
Service List

Hearing Program

 

Transcripts

 

PARTIES AND INTERVENORS

Applicant - Cellco Partnership d/b/a Verizon Wireless
Exhibits
Affidavit of Public in the Norwalk Hour, 03/20/23
Applicant's Responses to Council Interrogatories, Set One, 05/18/23

 

Procedural Correspondence

 

Motions and Objections
Applicant's Motion for Protective Order, 03/20/23
>Affidavit of Tim Parks in Support of Protective Order, 03/20/23
>Protective Order
Applicant's Withdrawal of Motion for Protective Order, 03/27/23

 

Briefs/Findings of Fact